Peikko has supplied Gravity Foundation Technology for the Monte D’Aria Wind Park. The farm is located in the Southern-Western part of the municipal territory of Serrapetrona (MC), Central Italy. The project consists of four wind turbines produced by MAIT Energy.

Peikko is responsible for the foundation design and structural calculations. The deliveries of Gravity Foundation solution comprise of steel components for the foundation. The solution from Peikko saves on materials used and decreases the total CO₂ emissions.

The development of Monte D’Aria Park is performed by Italian domestic company MAIT Energy. The company Mait Spa from Osimo realized the wind power plant, mainly specialized in industrial drilling machines and in well drilling. EMA Switchboards is one of the equipment suppliers chosen for this project.

EMA switchboards provided medium voltage switchboards used to connect the wind power plant to the Enel electric network and the equipment to measure the electric power produced by the wind turbines.

The annual production of the Monte D'Aria Wind farm estimated on the base of the collected wind data, will be 16GWh, equal to a 0.25% of the electric energy consumption of the Marche region. The wind power plant in Serrapetrona will be a state-of-the-art plant, in fact the wind turbines are latest generation and will be able to maximize electric power production.

Lire la suite down-arrow.png

Détails du Projet

Développeur:
MAIT Spa
Designer structurel:
Peikko Group (foundation only)
Année de réalisation:
2013
Année de livraison:
2014
Nombre de turbines:
5
Fabricant de turbine:
MAIT Spa
Puissance de la turbine, MW:
2
Taille de la turbine, m:
90