The deliveries comprise Anchor Bolts, Anchor Cage, Headed studs, Steel formwork and foundation reinforcement. Peikko’s turn-key project delivery introduces foundation design with 3 meter extension for higher hub height, all foundation components, and installation including concreting. The deliveries and installation started in December 2016 and the foundations will be finished during spring 2017.
The Harrström wind park is developed by Harrström Vinpark AB. Vestas delivers 4 pcs of V90 3 MW turbines with hub heights of 100 meters. The turbines will be installed right after foundation are completed and the wind park will be operational before summer 2017.